Westchester County Legislator Gordon Burrows Provides Update on Palmer Road Bridge

By Staff
Sep. 25, 2019: Westchester County Legislator Gordon A. Burrows said in a document sent to MyhometownBronxville.com on September 19, 2019, that "we are almost at the completion of phase one" of the Palmer Road Bridge. He also provided the following timeline and information.
- "September 27, 2019: stage 1 will be complete and phase 2 will begin. The road closure will reverse and the current sidewalk that is closed will reopen and the south sidewalk will close.
- On November 27, 2019, the day before Thanksgiving: the bridge will be reopened for two-way traffic.
- Northside sidewalk will remain open; southside sidewalk will remain closed.
- The stone facing on the bridge WILL BE reattached but dependent on temperature will determine when that will take place."
Pictured here: Palmer Road Bridge on September 20, 2019.
Photo by N. Bower
Editor's note: As a public service, MyhometownBronxville publishes articles from local institutions, officeholders, and individuals. MyhometownBronxville does not fact-check statements therein, and any opinions expressed do not necessarily reflect the thinking of its staff.